Dec 2010:WRG South East Regional – 3 year Framework Agreement

Client: Waste Recycling Group Limited
Location: South East region
Contract Dates: 2011 to 2013
Contract Value: c.£5m/annum

Description: Engineering works on WRG Landfill sites within their South East Region over a 3 year period. Initial Works in 2011 consist of 21Nr projects spread over 13 sites within the region.

Works comprise the following:

Formation of new engineered landfill cells

  • Bulk earthworks to form required formation levels
  • Placement of clay liner
  • Installation/welding of HDPE geomembrane liner
  • Installation of geomembrane protection material
  • Placement of stone leachate layer
  • Installation of leachate drainage systems and manholes

Capping existing landfill cells

  • Preparation of existing landfilled material to receive capping material
  • Excavation of site won material to form permanent capping , or
  • Installation/welding of HDPE geomembrane liner
  • Installation of geomembrane protection material
  • Placement of restoration material (subsoil/topsoil)

Enabling Works

  • Stripping topsoil to enable access/haul roads to be constructed.
  • Construction of haul roads
  • Installation of surface water ditches/lagoons