Retrofit Solid Waste Disposal Facility, Barbados
| Scheme |
Retrofit Solid Waste Disposal Facility |
|---|---|
| Client |
Government of Barbados; Sanitation Service Authority |
| Location |
Greenland, Barbados |
| Value |
BBD$17.5 million |
| Contract |
FIDIC |
| Duration |
9 months |
The scope of this project by the McArdle Group included the construction of a new landfill facility for the Island of Barbados, including all necessary infrastructure, and involved:
-
170,000 cm of excavation
-
100,000 cm of reworked clay liner
-
Supply and installation of 108,500 m2 of geotextile
-
Transportation and installation of 20,500 tonnes of leachate drainage stone
-
Supply and installation of 1,100 lm of leachate collection pipe
-
Supply and construction of scale house and weight scales
-
Supply and construction of 11,000 sm of rip-rap lined channels
-
Asphalt access roads
-
Weighbridge
-
Offices
-
Services and fences