M25 Widening Junction 12-15

Scheme M25 Widening Junction 12-15 and Heathrow Terminal 5 Spur Stage 2
Client Balfour Beatty Major Projects Ltd for the Highways Agency and Heathrow Airport Ltd
Location Surrey
Value Earthworks value: £8.3 million
Recycling value: £3 million
Contract NEC option D - Bulk Earthworks & Road Construction
NEC option B - Materials Supply
Duration 24 months

The scope of this project by the McArdle Group involved widening the existing 3- and 4-lane motorway to 4, 5 or 6 lanes in each direction, and stage 2 construction of the spur road into Terminal 4.

Principal activities by McArdle comprised bulk earthworks, reinforced coils, structures fills, road construction, crushing and screening materials for recycling into the work, topsoiling and landscaping.