// News

Home » News » T5C Baggage Transfer - Eastern Interface Building

T5C Baggage Transfer - Eastern Interface Building

31 Jul

31 July 2009

Third Phase of excavation work underway

 

McArdle will be starting the third phase of excavation work at Heathrow on the 3rd August 2009. The Eastern Interface Building is the next section of work McArdle have negotiated with Ferrovial Agroman Airports (UK) Limited as part of their contract to provide a baggage transfer system for Heathrow’s T5.

The Contract is worth £800k and work will include excavating over 7000m3 of mixed material from beneath Heathrow and disposing off site. This will be coordinated around Ferrovial who will be constructing a concrete chamber with intermediate floors as the work proceeds.

-
-
-
- - - - - - -