June 2011:A21 Lower Haysden Embankment Slip repairs

Client:Balfour Beatty Mott MacDonald

Location:A21 Lower Haysden Embankment Slip

Contract Value:£30k

Duration:2 weeks

Scope of works is Working under a traffic management scheme involving one lane closure, localised repairs to the lower slope face of a soil nailed embankment by infilling with mass concrete and replacement of the top 1.2m by excavating in benches and backfilling with Class 6I fill and Geogrid.