C2-C4 remediation and river walkway works

Client: St George Central London Ltd
Value of contract: £2 million

This project was part of a series of contracts successfully completed by the McArdle Group at Imperial Wharf, a prestigious residential development on the banks of the Thames.

Works undertaken during the five-month contract period included:

  • Bulk earthworks involving the segregation and stockpiling of contaminated soils, installation of a capillary layer
  • Disposal of contaminated soils to appropriate landfill site
  • Recycling of broken out concrete through crushing and screening
  • Pile probing and removal of obstructions
  • Pumping and processing of contaminated groundwater
  • Pile mat construction
  • Hard and soft landscaping to river walkway