Barrier Lining Pebsham Northth Landfill Site

Scheme:Pebsham Nth Landfill Site,

Client:DMD Plant

Location:Kent, UK

Value:£ 20,000

Contract:Lump Sum price, DMD Form with Amendments

Duration:4 weeks commencing June 2010

Scope:

The works included the installation only of 15,000m2 of 2mm HDPE liner and Geotextile liner for the construction of a new cell at the Pebsham Landfill Site.

All works work installed, tested and approved by the resident CQA Manager and to the Specifications as directed by the Environment Agency.