A21 Embankment Slip Repair

McArdle Stabilisation uses specialist capability to solve slip in tight working area

A21 Embankment slip repair

Benching in and laying the drainage blanket

McArdle Stabilisation were contacted by Interroute to repair an embankment along the A21 Sevenoaks bypass.

A total of 3,000m3 of material was excavated, modified using lime stabilisation techniques and re-compacted back into the works over a time period of four weeks.

The reinstatement works also involved installation of a drainage blanket and was to the clients design.